See below for latest News and progress with Stage 1, and final track plan.
Stage 1 Track Reconfiguration for Practice Day use only.
Stage 2 Track Reconfiguration for full Competition use (1st Draft approx 1,600 Metres - currently 1,450m).
Stage 2 Track Configuration - Final layout (for full competition use - 1,600 Metres).
The Management Committee met with Council Represenatives on 21/12/11 to discuss the necessary work required to be able to re-open the facility. This will be achieved in 2 stages described below; and progress in line with the Council set timetable (link below).
9/1/12 - the Mgmt Com'tee met with Council Reps and agreed to draft track plans (see links on this home page)
23/1/12 - the Mgmt Com'tee met with Council Reps and formailsed Stage 1 track plans and timetable for completion (rain/weather permitting).
8/2/12 - the Mgmt Com'tee met with Council Reps, signed off Stage 1 track plans, and agreed to the extent of the new noise barrier that will be part of Stage 2. Council contractors will commence excavation works on Monday 13/2 in order to lower the track in front of the canteen area. This works is scheduled to take 2 weeks, and when completed, the Club will re-instate the track and irrigation lines through the excavated area.
Stage 1 will necessitate a temporary track reconfigeration in areas that are deemed to cause too much noise to escape from the facility. When these works are completed, it's expected that Council will allow the Club to recommence practice days - but not competition race days.
Stage 2 will necessitate a comprehensive track reconfigeration, including the relocation of the start gates & score tower (and maybe other structures). When these works are completed, it's expected that Council will allow the Club to recommence competition racing.
Gold Coast City Council timetable for works at Stanmore Park.
Track Closed this Weekend. The track is closed for riding until advised by Council that we can re-commence activities. The Club expects to receive official notification from Council regarding their plan and timetable for re-opening, in the near future. Once this information is known, it will then be posted on the web site.